輕鋼龍骨石膏板天花吊頂施工工藝(yi) 打造(zao)時尚美觀天花
步驟一:清理現場:對施工現場墻(qiang)、地面、灰塵、垃圾進行清理。
步驟二:彈線定位:根據(ju)設計及現場要求、確定50cm水平(ping)線(xian),用(yong)尺(chi)量至頂面設計標高線(xian),在四周墻面彈頂面水平(ping)線(xian)(水平(ping)線(xian)應(ying)以付(fu)龍(long)骨(gu)底面為準),然(ran)后畫出(chu)龍(long)骨(gu)位置線(xian)和吊點(桿(gan))布(bu)置線(xian)。
步驟三:安裝吊桿
a.角(jiao)(jiao)鐵(tie)吊(diao)件(jian)及吊(diao)筋加工:角(jiao)(jiao)鐵(tie)吊(diao)件(jian)采用L30*30角(jiao)(jiao)鐵(tie)加工,在角(jiao)(jiao)鐵(tie)面(mian)上劃出(chu)中心線(xian),對(dui)應(ying)打(da)出(chu)一排 10或 8的(de)孔(kong)(kong)、孔(kong)(kong)距45mm左(zuo)右,再將角(jiao)(jiao)鐵(tie)分段切割下(xia)來。不上人吊(diao)件(jian)可用小角(jiao)(jiao)鐵(tie)制作, 吊(diao)點(dian)(dian)應(ying)在屋面(mian)板下(xia)均勻(yun)分布(bu)(施(shi)工前應(ying)對(dui)現(xian)場(chang)進行檢查,布(bu)點(dian)(dian)應(ying)避(bi)開頂(ding)面(mian)空調風筒及各(ge)種(zhong)管道(dao),若避(bi)不開時可采取角(jiao)(jiao)鐵(tie)補充(chong)吊(diao)點(dian)(dian)),大(da)面(mian)積或上人吊(diao)頂(ding)吊(diao)點(dian)(dian)間距為(wei)≤1000mm,一般(ban)吊(diao)頂(ding)的(de)吊(diao)點(dian)(dian)間距為(wei)≤1200mm,用電錘在頂(ding)上打(da)孔(kong)(kong),放置(zhi)膨脹栓擰緊固定于頂(ding)面(mian)上。
b.根據(ju)頂(ding)面(mian)水平線量出(chu)吊(diao)(diao)(diao)筋加工(gong)尺(chi)寸,若頂(ding)面(mian)平整較差(cha),吊(diao)(diao)(diao)桿(gan)(gan)長度(du)(du)不(bu)(bu)能(neng)統(tong)一(yi)時可拉通(tong)線,按實際(ji)尺(chi)寸逐—·找出(chu)吊(diao)(diao)(diao)桿(gan)(gan)長度(du)(du),吊(diao)(diao)(diao)桿(gan)(gan)可采取兩節(jie)搭(da)(da)接(jie)(jie)(焊(han)接(jie)(jie))方式,搭(da)(da)接(jie)(jie)長度(du)(du)大(da)于吊(diao)(diao)(diao)桿(gan)(gan)直徑(jing)的8倍(bei),將吊(diao)(diao)(diao)桿(gan)(gan)下端套(tao)扣(套(tao)絲時應(ying)加機油,以保證套(tao)扣質量)套(tao)絲長度(du)(du)不(bu)(bu)小于50mm,然后將吊(diao)(diao)(diao)桿(gan)(gan)與角鐵(tie)吊(diao)(diao)(diao)件焊(han)接(jie)(jie),焊(han)接(jie)(jie)要精心操作,不(bu)(bu)得馬虎(hu),焊(han)接(jie)(jie)部(bu)位應(ying)飽(bao)滿,確保足夠的強度(du)(du)。
c.角鐵吊(diao)(diao)件及吊(diao)(diao)桿(gan)加工完(wan)成后,按頂面水平線,付龍骨底面拉通線,為吊(diao)(diao)桿(gan)安裝基準線,進行吊(diao)(diao)桿(gan)安裝,吊(diao)(diao)桿(gan)間距應(ying)均勻,靠墻邊吊(diao)(diao)桿(gan)距墻不得(de)大于200mm,安裝后的(de)吊(diao)(diao)桿(gan)應(ying)垂直并在一條線上,刷防銹(xiu)漆兩(liang)遍,應(ying)按設計要求(qiu)調整起拱(gong)(gong)高度(起拱(gong)(gong)按短向跨度的(de)3-5/1000)。
d.吊(diao)桿(gan)(gan)距(ju)主龍骨端部(bu)距(ju)離不得大于300mm,當大于300mm時(shi)應(ying)(ying)增加吊(diao)桿(gan)(gan)。當吊(diao)桿(gan)(gan)與(yu)設備(bei)相遇時(shi),應(ying)(ying)調整并增設吊(diao)桿(gan)(gan),并不得與(yu)設備(bei)共(gong)用(yong)吊(diao)桿(gan)(gan)。
步驟四:龍骨安裝:主龍(long)(long)(long)骨應頂(ding)住墻面(mian)(mian),副龍(long)(long)(long)骨應緊貼墻面(mian)(mian)。用(yong)吊件(jian)(jian)與(yu)主龍(long)(long)(long)骨連接,同時(shi)擰緊吊件(jian)(jian)螺(luo)母,使(shi)主龍(long)(long)(long)骨安裝牢固(gu),主龍(long)(long)(long)骨連接件(jian)(jian)要錯位安裝以(yi)保證有足(zu)夠的穩(wen)定(ding)性(xing)。大面(mian)(mian)積吊頂(ding)每隔12m在主龍(long)(long)(long)骨上部(bu)焊接橫撐大龍(long)(long)(long)骨一道,以(yi)加強主龍(long)(long)(long)骨側面(mian)(mian)穩(wen)定(ding)性(xing)及吊頂(ding)的整體(ti)性(xing)。付龍(long)(long)(long)骨安裝用(yong)吊掛(gua)(件(jian)(jian))與(yu)主龍(long)(long)(long)骨固(gu)定(ding),吊掛(gua)必須用(yong)鉗子夾(jia)緊使(shi)付龍(long)(long)(long)骨緊貼主龍(long)(long)(long)骨,大面(mian)(mian)積或上人(ren)吊頂(ding)間距300mm,一般吊頂(ding)的間距401mm(己考(kao)慮石膏板(ban)(ban)留(liu)3mm縫(feng)隙),橫撐付龍(long)(long)(long)骨間距1500mm,用(yong)于石膏板(ban)(ban)中間及寬(kuan)邊(1200mm)接頭(tou)處(chu)、平(ping)行于主龍(long)(long)(long)骨用(yong)支托與(yu)付龍(long)(long)(long)骨連接固(gu)定(ding)。
步驟五:安裝石膏板:先(xian)檢查龍骨安裝是否平整(zheng),牢(lao)固,配(pei)件安裝是否正(zheng)確,然后才可進行石(shi)膏板(ban)(ban)(ban)安裝,首(shou)先(xian)根據(ju)龍骨間距(ju)在石(shi)膏板(ban)(ban)(ban)面(mian)上彈(dan)出(chu)龍骨中(zhong)心線,一(yi)般(ban)先(xian)從頂棚中(zhong)心向周(zhou)圍鋪設,固定石(shi)膏板(ban)(ban)(ban)的(de)高(gao)強(qiang)自(zi)攻絲間距(ju)不大于150--170mm,由板(ban)(ban)(ban)中(zhong)間向四(si)周(zhou)固定,強(qiang)攻絲距(ju)板(ban)(ban)(ban)長邊(bian)10--15mm,短(duan)邊(bian)15--20mm,沉入板(ban)(ban)(ban)內(nei)1-2mm不得損壞紙(zhi)面(mian),應(ying)注意留(liu)3mm板(ban)(ban)(ban)縫(1200短(duan)邊(bian)留(liu)4--6mm縫),四(si)周(zhou)墻(qiang)邊(bian)留(liu)10mm左(zuo)右縫隙(xi)以防(fang)伸縮(suo)變(bian)形,應(ying)錯(cuo)位(錯(cuo)開半板(ban)(ban)(ban))安裝。
步驟六:按質量要求及檢查方法檢查:
a.輕(qing)鋼龍骨安裝位置正確,牢固(gu),無松動,吊桿做防銹處理。
b.石膏板應(ying)表面平整無污染(ran),反銹,無脫層、翹(qiao)曲、折裂等(deng)缺陷。